Construction
Updates
41st St & Beaver Ave Project
The 41st St & Beaver Avenue construction project has been split into 5 phases. The picture below shows the final state of the completed project. Here is a link to the official Des Moines construction page

Phase 2
Update 5/19/2025: Our Drive-Up is back open!!
The construction project is moving along a quick pace. Beginning May 12, 2025, our North driveway and patio are being torn out and repaved. We are temporarily closing our drive-up while this piece is completed. We are hopeful that this phase will only last one week. Our South driveway is now available for use as well as the West entrance/exit via the Westminster church parking lot. We sincerely appreciate your patience during this time.

Phase 4
Details coming soon

Phase 1
As of April 13, 2025, we are in Phase 1. During this phase our South driveway will be torn out and repaved. Customers can still enter using our North driveway. Additionally, there will be an exit out of the west end of the parking lot into the Westminster Church parking lot. Our drive-through customers will pull straight forward after placing their order and then exit into the Westminster Church parking lot after your treats have been delivered. See picture below.

Phase 3
Details coming soon

Phase 5
Details coming soon